06Chapter 6 · Delivery
From signature to sunlight.
A short, ordered path: execute the agreement, clear the conditions precedent, build and commission, then begin the 15-year service term at operational commencement.
Agreement & customer details
Clause 5 / Schedule 1Execute the agreement and confirm the outstanding Schedule 1 customer details.
Relative start point
Conditions precedent
Clause 5Satisfy conditions precedent so the project can proceed.
Normally within 30 days of signature, unless extended in writing
Confirm site & financial conditions
Clause 5 / Clause 8Confirm site rights, the security (bank guarantee) requirement, permits, structural suitability and no material adverse financial change.
Part of conditions precedent
Build & commission
Clause 8Design, procurement, installation, testing, metering verification and commissioning.
Following conditions precedent
Operational commencement
Clause 8 / Clause 34UtCS issues written commencement notice once the system is operational.
Target within 180 days after all conditions precedent are fulfilled, subject to stated exceptions
Service term begins
Clause 6The 15-year initial service term starts at operational commencement.
At commencement
Operate, report & decide
Clause 6 / Clause 23Ongoing maintenance, annual sustainability reporting, renewal or end-of-term decisions.
Across the term
Timings are targets, with stated exceptions
The 10-year window sits inside a 15-year term